The Northeast Ohio Regional Sewer District will host our Euclid Creek Tunnel Community Meeting tonight, March 19. The meeting, regularly scheduled for the third Tuesday of each month, begins at 6:00 p.m. and is held at the Memorial-Nottingham Branch of the Cleveland Public Library (17109 Lake Shore Blvd.).
For those interested in updates, but unable to attend the meeting, a copy of the PowerPoint presentation will be posted to the blog within the next several days.
PLEASE NOTE: The date, time and/or location for our April meeting may change. Please subscribe to the Euclid Creek Newsletter or return to the Euclid Creek Blog for updates.
Thank you and I hope to see you tonight.
Tuesday, March 19, 2013
Thursday, March 14, 2013
Secant Pile Drilling Coming To An End
The secant pile drilling at site 3-1 will be coming to completion late this week or early next week. As the contractor completes this phase of the work, he will begin removing his equipment from the site. Both the blue and yellow crane and drill rig will be disassembled and trucked off site. We expect this to take the majority of next week.
Once the secant pile contractor is gone, the excavation contractor will begin to mobilize his excavators and cranes to the site. I will detail this work once we get closer to it.
Once the secant pile contractor is gone, the excavation contractor will begin to mobilize his excavators and cranes to the site. I will detail this work once we get closer to it.