Thursday, March 14, 2013

Secant Pile Drilling Coming To An End

The secant pile drilling at site 3-1 will be coming to completion late this week or early next week.  As the contractor completes this phase of the work, he will begin removing his equipment from the site.  Both the blue and yellow crane and drill rig will be disassembled and trucked off site.  We expect this to take the majority of next week.

Once the secant pile contractor is gone, the excavation contractor will begin to mobilize his excavators and cranes to the site.  I will detail this work once we get closer to it.