Monday, April 15, 2013
Construction Update 4/15 (LANE CLOSURE)
There will be construction activity later this week or early next week in E 156th St near the entrance to the 3-2 fenced in area. One lane of traffic will be closed to allow for the work activities, flaggers will be present ensuring the smooth flow of traffic in each direction. This work includes the drilling of the dewatering wells that will be utilized in the future excavation of the Structure 3-4. Once the drilling is complete all lanes will be reopened until the actual excavation begins (July). The equipment to be used is currently working inside the fenced in area on the North side.