Friday, May 31, 2013

E 156th Update

East 156th will temporary be reopened early next week.  The work installing the solider piles (vertical  steel beams used to support the ground while the ground is being excavated) and placing dewatering pipes below grade is complete.  The portion of the street that was disturbed for the above will be filled with 304 limestone (small diameter stone).  Please use caution while traveling over this area.  The road will be closed of approximately 15 months starting mid to late July at which time the detour that was previously utilized will be in effect.