Tuesday, November 13, 2012

11/13/12 Update for E 156th and Beulah Park

Winter has officially arrived today with snow falling on our work sites along Euclid Creek Tunnel

Work at the location of Shaft 3-1 will continue with tree removal and branch chipping.

Work will continue at the intersection of East 156th and Lakeshore and last through mid December. 

Please keep in mind the that sidewalk is still closed on the west side of E 156th due to the ongoing activities withing the fenced in area but will be replaced in the future.  Also there may be short durations of traffic rerouting to allow for construction activities for the safety of the residents and the crews.  Any interruption will be kept short as possible.