Monday, December 10, 2012

12/10/12 Update for E 156th and Beulah Park

Expect things to be a little quite for the next few days at the 3-1 site; the guide wall has been installed and is curing.  The secant pile contractor should be mobilizing to the site in the next few weeks, we will certainly keep everyone posted regarding this as some of the truck used to drop off the equipment are big ones may affect traffic routes for a day or two. 

Please keep in mind the that sidewalk is still closed on the west side of E 156th due to the ongoing activities withing the fenced in area but will be replaced in the future.  Also there may be short durations of traffic rerouting to allow for construction activities for the safety of the residents and the crews.  Any interruption will be kept short as possible