Thursday, December 13, 2012

12/13 Update

The secant pile contractor will begin mobilizing to the site next week.  A 100 ton crane will be delivered on Tuesday the 18th.  This crane will come on a few trucks and will be assembled once on site.  Later in the week, the secant pile rig (Bauer BG40) will be delivered.  There may be some slight traffic interruptions with the trucks making their way to the site, please drive with care.

Please keep in mind the that sidewalk is still closed on the west side of E 156th due to the ongoing activities withing the fenced in area but will be replaced in the future.  Also there may be short durations of traffic rerouting to allow for construction activities for the safety of the residents and the crews.  Any interruption will be kept short as possible.