The construction of the guide wall will continue through the end of the week at the 3-1 site.
I have been told that many of our readers would like to know more about the secant pile wall that will be installed at 3-1. I will attempt to detail this process next week.
Please keep in mind the that sidewalk is still closed on the west side of E 156th due to the ongoing activities withing the fenced in area but will be replaced in the future. Also there may be short durations of traffic rerouting to allow for construction activities for the safety of the residents and the crews. Any interruption will be kept short as possible